- SUB I -
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1) Sanitary line work continues 2) Installation of curb, stone and base paving continues 3) Steel and decking erection continues for columns and beams for all levels of the new addition. 4) Due to some weather delays, it is estimated that delivery of structural steel will continue through December 4th, about 3 days behind the schedule previously distributed. It is possible (not probable) this lost time will be made up through the Thanksgiving break, contingent upon scheduling with the manufacturer. Next construction schedule update will be on or around December 1st. Please note: Delivery trucks for the steel, offloading and erecting it continues. Will continue to be noisy and congested on Aquia Creek Lane. |
||
|---|---|---|
| Construction Activity | Construction Start | Anticipated Occupancy |
| PHASE 1 | ||
Academic Advising Expansion, Level 3 |
8/2/2010 |
12/12/2010 |
TSOA (Technical Service Office of Admissions), Level 3 |
8/2/2010 |
12/12/2010 |
Cash Office Expansion, Level 1 |
8/2/2010 |
12/22/2010 |
| General Enrollment Space, Level 1 | 8/2/2010 |
12/22/2010 |
Registrar's Storage, Level 1 |
8/2/2010 |
12/22/2010 |
MRRC, Level 2 |
8/2/2010 |
12/18/2010 |
ODPS, Level 2 |
8/2/2010 |
12/18/2010 |
Student Centers Office Area, Level 1 |
8/2/2010 |
12/22/2010 |
| PHASE 2 (Proposed) | ||
Disability Testing Rooms, Level 3 |
12/30/2010 |
5/12/2011 |
All Cluster Space (except for Disability Testing Rooms, Level 3 |
12/30/2010 |
5/12/2011 |
Meeting Room Renovations, Level 3 |
12/30/2010 |
5/12/2011 |
Career Development Expansion, Level 3 |
12/30/2010 | |
PEP (moves to SUB I existing Level), Level 1 |
12/30/2010 |
5/24/2011 |
LGBTQ, Level 2 |
12/30/2010 |
5/24/2011 |
EIP (moves to SUB I existing Level 1), Level 1 |
12/30/2010 |
5/24/2011 |
Disability (moves to SUB I existing Level 2), Level 2 |
12/30/2010 |
5/12/2011 |
Student Health Expansion |
12/30/2010 |
5/19/2011 |
- SUB II -Revised 9/8/09
|
|---|
CONSTRUCTION
This page provides updates/progress, revisions, and important dates relative to the construction taking part in SUB I & SUB II.
SUB I:
Proposed Schematic Renderings:
5-19-09
7-1-09
9-21-09
Construction Site Images
SUB II:
Proposed Schematic Renderings:
5-19-09
7-1-09
Contruction Site
Images