CONSTRUCTION ACTIVITY FOR THE WEEK OF NOV. 17 – NOV. 30


1)    Sanitary line work continues

2)    Installation of curb, stone and base paving continues

3)    Steel and decking erection continues for columns and beams for all levels of the new addition.

4)    Due to some weather delays, it is estimated that delivery of structural steel will continue through December 4th, about 3 days behind the schedule previously distributed. It is possible (not probable) this lost time will be made up through the Thanksgiving break, contingent upon scheduling with the manufacturer. Next construction schedule update will be on or around December 1st.

Please note:  Delivery trucks for the steel, offloading and erecting it continues. Will continue to be noisy and congested on Aquia Creek Lane.


Construction Activity Construction Start Anticipated Occupancy
PHASE 1    
Academic Advising Expansion, Level 3
8/2/2010
12/12/2010
TSOA (Technical Service Office of Admissions), Level 3
8/2/2010
12/12/2010
Cash Office Expansion, Level 1
8/2/2010
12/22/2010
General Enrollment Space, Level 1
8/2/2010
12/22/2010
Registrar's Storage, Level 1
8/2/2010
12/22/2010
MRRC, Level 2
8/2/2010
12/18/2010
ODPS, Level 2
8/2/2010
12/18/2010
Student Centers Office Area,
Level 1
8/2/2010
12/22/2010
PHASE 2 (Proposed)    
Disability Testing Rooms, Level 3
12/30/2010
5/12/2011
All Cluster Space (except for Disability Testing Rooms, Level 3
12/30/2010
5/12/2011
Meeting Room Renovations,
Level 3
12/30/2010
5/12/2011
Career Development Expansion,
Level 3
12/30/2010
PEP (moves to SUB I
existing Level), Level 1
12/30/2010
5/24/2011
LGBTQ, Level 2
12/30/2010
5/24/2011
EIP (moves to SUB I existing Level 1), Level 1
12/30/2010
5/24/2011
Disability (moves to SUB I existing Level 2), Level 2
12/30/2010
5/12/2011
Student Health Expansion
12/30/2010
5/19/2011

- SUB II -

Revised 9/8/09
Proposed Schematic Renderings: 5-19-09 / 7-1-09
Construction Site Images

Construction Activity Construction Start Anticipated Occupancy
PHASE 1    
Retail Food Operation, Level 2
2/1/2010
8/15/2010
Dining Area, Level 2
2/1/2010
8/15/2010
Student Activites and Organizations, Level 2
2/1/2010
8/15/2010
Entertainment/ Gaming Area, Level 2
2/1/2010
8/15/2010
LEAD, Level 2,
2/1/2010
8/15/2010
OFPS, Level 2
2/1/2010
8/15/2010
Student Media, Level 1
2/1/2010
8/15/2010
Literary Journals, Level 1
2/1/2010
8/15/2010
General Cluster Space (shared by all groups), Level 1
2/1/2010
8/15/2010

 

 

CONSTRUCTION

This page provides updates/progress, revisions, and important dates relative to the construction taking part in SUB I & SUB II.

SUB I:
Proposed Schematic Renderings:
5-19-09

7-1-09
9-21-09

Construction Site Images

 

SUB II:
Proposed Schematic Renderings:
5-19-09
7-1-09

Contruction Site
Images